It’s here! We are moving quickly on the demolition of the construction area.
- The block walls around the site have been torn down.
- Jim Skaas gave us his backhoe to use throughout our project for free and also agreed to operate it—this will save us thousands of dollars.
- The construction fence has been installed.
- The salvage efforts of the houses have worked out better than we anticipated. This is saving us much money on dumping as well as meeting the city’s green building ordinance.
- We are in the process of finding a good dump truck for our construction.
- Many men have come to help with the clean up of the demo.
Please continue to be in prayer as we move on in our demo, grading, and soon construction of our new building.