September 26

The main sewer project is moving right along!

  • All the pipe has been laid, and the manholes should be set this week.
  • We received our material and have almost completed the trench. When the trench is finished, we will be able to start dropping the pipe.
  • September 13 Pictures
  • September 23 Pictures

Our power pole reroute is almost complete.

  • Edison also came out and installed the new pole and transformer that will feed our property.
  • The meters have been installed and the power is hot.
  • We will do the cutover very soon and the existing pole will be removed thereafter.