The main sewer project is moving right along!
- All the pipe has been laid, and the manholes should be set this week.
- We received our material and have almost completed the trench. When the trench is finished, we will be able to start dropping the pipe.
- September 13 Pictures
- September 23 Pictures
Our power pole reroute is almost complete.
- Edison also came out and installed the new pole and transformer that will feed our property.
- The meters have been installed and the power is hot.
- We will do the cutover very soon and the existing pole will be removed thereafter.