Thank you for doing your part! In the past month, we have seen much progress thanks to our faithful men and the help of our CLAIM teams:

  • Framing on the exterior walls is about 60% complete.
  • Mezzanine decking is 95%complete.
  • All retaining walls are poured.
  • Waterproofing of retaining wall is complete.
  • Inspection of retaining wall waterproofing and drainage pipe has passed city inspection.
  • Digging of elevator pit is 80% complete.
  • Painting of gymnasium steel is about 40% complete.
  • Seventy-five percent of all window and door headers are built.
  • The grading is complete on 33rd street side for machinery to drive on.
  • The construction shed, storage shelf, and miscellaneous supplies are moved to a new location so we can start the new entrance walkway.
  • All broken plumbing pipes are fixed.
  • All safety handrails are installed on 2nd floor and around elevator pit.

Please continue to earnestly pray,  volunteer, and give to see the building built for God’s glory!  We need as many volunteers as  possible! If you can volunteer or help in any way, please see Bro. Rathana Sin or you can reach him at (562)-424-7714 ext. 311.