Our 52 Day Campaign has only two more weeks left! Many have come out and much has been accomplished including:
- 2nd floor window glass being installed
- Wall sheathing pick up work continues.
- Exterior framing continues.
- Interior 1st and 2nd floor framing continues.
- Exterior and Interior rough electrical continues.
- Mansard wall sheathing is complete.
- Mansard roof sheathing on the north wall is complete.
- Windows and storefronts: Installation continues.
- Framing the 2nd floor elevator walls complete.
- Exterior and Interior rough electrical continues.
- Framing the stair walls on the 33rd entrance.
- Clock tower framing continues.
- Fascia boards is complete.
- Canopy sheathing complete
- Window insulation started
A special thank you to those who came out and to the scores and scores who have committed to come during our 52 Day Campaign! There’s still time and a great need for YOUR HELP!
Please pray for God’s continued hand on our project and specifically, the 52 Day Campaign.