52 Day Campaign: Week 7

Our 52 Day Campaign has only two more weeks left! Many have come out and much has been accomplished including:

  1. 2nd floor window glass being installed
  2. Wall sheathing pick up work continues.
  3. Exterior framing continues.
  4. Interior 1st and 2nd floor framing continues.
  5. Exterior and Interior rough electrical continues.
  6. Mansard wall sheathing is complete.
  7. Mansard roof sheathing on the north wall is complete.
  8. Windows and storefronts: Installation continues.
  9. Framing the 2nd floor elevator walls complete.
  10. Exterior and Interior rough electrical continues.
  11. Framing the stair walls on the 33rd entrance.
  12. Clock tower framing continues.
  13. Fascia boards is complete.
  14. Canopy sheathing complete
  15. Window insulation started

A special thank you to those who came out and to the scores and scores who have committed to come during our 52 Day Campaign! There’s still time and a great need for YOUR HELP!

Please pray for God’s continued hand on our project and specifically, the 52 Day Campaign.