On lot sewer project
- This week we had several men come in on 2nd shift and work until the evening to dig and lay our sewer pipe.
- John Ellis of Ellis Equipment came and volunteered on Saturday to operated the backhoe.
Electrical reroute project
- We have completed the rough in at the existing electric room. Everything is prepped and ready for the new service. The trench is 75% complete. Once completed, we can lay the pipe and pull the wire. The Edison pole will be removed shortly after that.
Main sewer project
- The main sewer line and four man holes have been installed, tested, and are now in use. Our contractor is cleaning the street and finishing the compaction.
- Paving will soon follow, and the street will be reopened very soon.
- We are also able to continue to save money by Hansen concrete, who will continue to allow us to dump all of the asphalt and concrete that was dug up during the sewer reroute projects.
- We will begin hauling out several loads of this material next week.