Almost Finished…
We are almost finished with the exterior framing. We are working to finish it by the end of this week. We encourage you to show up to all our work parties and anytime you can help out. The new CLAIM team will be here on October 24th and we can use all the extra help we can get.
Thank you…
Thank you for doing your part! In the past month, we have seen much progress thanks to our faithful men and the help of our CLAIM teams:
- Framing on the exterior walls is about 60% complete.
- Mezzanine decking is 95%complete.
- All retaining walls are poured.
- Waterproofing of retaining wall is complete.
- Inspection of retaining wall waterproofing and drainage pipe has passed city inspection.
- Digging of elevator pit is 80% complete.
- Painting of gymnasium steel is about 40% complete.
- Seventy-five percent of all window and door headers are built.
- The grading is complete on 33rd street side for machinery to drive on.
- The construction shed, storage shelf, and miscellaneous supplies are moved to a new location so we can start the new entrance walkway.
- All broken plumbing pipes are fixed.
- All safety handrails are installed on 2nd floor and around elevator pit.
Please continue to earnestly pray, volunteer, and give to see the building built for God’s glory! We need as many volunteers as possible! If you can volunteer or help in any way, please see Bro. Rathana Sin or you can reach him at (562)-424-7714 ext. 311.
Exterior Walls, Mezzanine, and Retaining Walls
The exterior walls are about 33% complete, the mezzanine is 90% complete, all retaining walls are complete, and the waterproofing of the retaining walls are about 90% complete, excavation of the elevator pit has begun also. We can use as many volunteers as possible. The second group of the CLAIM team are also here. If you can help or volunteer in any way, please see Rathana Sin or you can reach him at 562-424-7714 ext. 311.
Framing Continues
The first group of CLAIM men are here. Our goal is to finish framing the interior and exterior walls by the end of November. This is a BIG goal and we need as many volunteers as possible. If you can volunteer or help out in any way (meals, cleaning, etc.), contact Rathana “Kevin” Sin or you can reach him at (562) 424-7714 ext. 311.
Here are several projects we are working on:
- the other 2 retaining walls
- Sealing the retaining walls
- Putting the steel studs up on walls
- Making our own steel clips by cutting some of our steel studs. This is saving us thousands of dollars.
- Men cleaning part of the steel of our gymnasium to paint the beam.
Thank you for doing your part by praying, giving, and volunteering to see the building built for God’s glory!