This week some roof insulation was installed, and one retaining wall was poured.
[vimeo 43287107]
Stay updated on our building progress!
This week some roof insulation was installed, and one retaining wall was poured.
[vimeo 43287107]
Most of this week was spent placing thin metal strips that will hold the insulation (inside the building) and roofing sheets (on top of the building).
It didn’t seem like much was done this week because all of the work this week has been in getting the roof ready. Below are some pictures of what was done.
The crew is just about done with the main steel beams. The roof could possibly be started next week.