Parking Lot Update Northwestern parking lot ready for concrete Footings installed on northeastern side of parking lot Ditches being dug on northeastern side of parking lot
Parking Lot Update South parking lot curb and ballards complete West parking lot curb Men measured for the northwestern curbs Men started on forms for curbs this week
Parking Lot and More! Anthony working on light post trenches Daniel Filling in the trenches Dirt compactor Balcony truss installation continued in the main auditorium
Building Progress Rebar for light posts Concrete poured for trash enclosure Balcony truss brackets are being installed Balcony truss brackets