We are almost finished with the exterior framing. We are working to finish it by the end of this week. We encourage you to show up to all our work parties and anytime you can help out. The new CLAIM team will be here on October 24th and we can use all the extra help we can get.
Tag: pictures
Exterior Walls, Mezzanine, and Retaining Walls
The exterior walls are about 33% complete, the mezzanine is 90% complete, all retaining walls are complete, and the waterproofing of the retaining walls are about 90% complete, excavation of the elevator pit has begun also. We can use as many volunteers as possible. The second group of the CLAIM team are also here. If you can help or volunteer in any way, please see Rathana Sin or you can reach him at 562-424-7714 ext. 311.
Framing Continues
The first group of CLAIM men are here. Our goal is to finish framing the interior and exterior walls by the end of November. This is a BIG goal and we need as many volunteers as possible. If you can volunteer or help out in any way (meals, cleaning, etc.), contact Rathana “Kevin” Sin or you can reach him at (562) 424-7714 ext. 311.
Here are several projects we are working on:
- the other 2 retaining walls
- Sealing the retaining walls
- Putting the steel studs up on walls
- Making our own steel clips by cutting some of our steel studs. This is saving us thousands of dollars.
- Men cleaning part of the steel of our gymnasium to paint the beam.
Thank you for doing your part by praying, giving, and volunteering to see the building built for God’s glory!
Two Bays Framed
We are framing our exterior walls and have completed 2 bays already. Next week, different CLAIM teams will be here to help us out. We can use some volunteers to help us out. See Bro. Rathana Sin to volunteer or reach him at 562-424-7714 ext. 311.
Parameter Framing
Enjoy some pictures of the framing of our exterior wall with the steel studs.