Framing

We are beginning to frame our exterior walls this week. We need as many volunteers as possible. If you can volunteer or help in any way, please see Bro. Rathana Sin or you can reach him at (562)-424-7714 ext. 311.

Thank you for doing your part! Please continue to earnestly pray, volunteer, and give to see the building built for God’s glory!

The pictures above is the very first steel stud to our exterior wall.

Retaining Walls

The retaining walls are complete. We can use some volunteers to help with our steel stud framing. The steel studs should be coming by the end of this week. Thank you for doing your part! Please continue to earnestly pray, volunteer, and give to see the building built for God’s glory! See Bro. Rathana Sin to volunteer.

Steel (Week 12)

The roof is almost complete, and the erection of the second floor has begun. Also, the last two retaining walls are almost complete.